Mold production Lead time
Product | Type of Mold | Specifications Approval |
Pattern Fabrication | Full-mold Casting |
3D Modeling |
CNC Work |
Polishing Assembling |
Die Spotting |
Try-out | Lead Time |
---|---|---|---|---|---|---|---|---|---|---|
Headliner | Cold forming or Thermoforming | 6 | 5 | 10 | 4 | 10 | 5 | 3 | 2 | 45 days |
Compression | 6 | 5 | 14 | 4 | 14 | 7 | 3 | 2 | 55 days | |
Trimming & Piercing | 14 | 7 | 14 | 12 | 20 | 16 | 5 | 2 | 90 days | |
Water jet JIG | 35 days | |||||||||
Checking Fixture | 35 days | |||||||||
Floor Carpet | Forming | 6 | 5 | 10 | 4 | 10 | 5 | 3 | 2 | 45 days |
Foaming | 10 | 5 | 10 | 4 | 12 | 9 | 3 | 2 | 55 days | |
Trimming & Piercing | 14 | 7 | 14 | 12 | 20 | 16 | 5 | 2 | 90 days | |
Forming+Trimming | 14 | 7 | 14 | 12 | 20 | 16 | 5 | 2 | 90 days | |
Water jet JIG | 35 days | |||||||||
Checking Fixture | 35 days | |||||||||
Wheel Guard | Forming | 6 | 5 | 10 | 4 | 9 | 6 | 3 | 2 | 45 days |
Trimming & Piercing | 10 | 5 | 14 | 7 | 20 | 12 | 5 | 2 | 75 days | |
Piercing Equipment | 35 days | |||||||||
Checking Fixture | 35 days | |||||||||
Luggage Side | Forming | 7 | 5 | 14 | 4 | 8 | 7 | 3 | 2 | 50 days |
Trimming & Piercing | 10 | 5 | 14 | 7 | 20 | 12 | 5 | 2 | 75 days | |
Forming+Trimming | 14 | 7 | 14 | 12 | 15 | 16 | 5 | 2 | 85 days | |
Checking Fixture | 35 days | |||||||||
Luggage Mat | Forming+Trimming | 6 | 5 | 14 | 4 | 14 | 7 | 3 | 2 | 55 days |
Checking Fixture | 35 days | |||||||||
Trunk Lid | Forming | 6 | 5 | 10 | 4 | 10 | 5 | 3 | 2 | 45 days |
Forming+Trimming | 6 | 5 | 14 | 4 | 11 | 5 | 3 | 2 | 50 days | |
Checking Fixture | 35 days | |||||||||
Partition Lower Upper |
Forming | 6 | 5 | 10 | 4 | 9 | 6 | 3 | 2 | 45 days |
Trimming & Piercing | 6 | 5 | 14 | 4 | 14 | 7 | 3 | 2 | 55 days | |
Forming+Trimming | 6 | 5 | 14 | 4 | 14 | 7 | 3 | 2 | 55 days | |
Checking Fixture | 35 days | |||||||||
Package Tray | Forming | 6 | 5 | 10 | 4 | 9 | 6 | 3 | 2 | 45 days |
Trimming & Piercing | 6 | 5 | 14 | 4 | 14 | 7 | 3 | 2 | 55 days | |
Piercing Equipment | 35 days | |||||||||
Checking Fixture | 35 days | |||||||||
Engine Hood | Thermoforming | 6 | 5 | 14 | 4 | 14 | 7 | 3 | 2 | 55 days |
Trimming & Piercing | 6 | 5 | 14 | 4 | 14 | 7 | 3 | 2 | 55 days | |
Checking Fixture | 35 days | |||||||||
Dash insulation pad |
Cold forming or Thermoforming | 6 | 5 | 10 | 4 | 10 | 5 | 3 | 2 | 45 days |
Foaming | 10 | 5 | 10 | 4 | 12 | 9 | 3 | 2 | 55 days | |
Trimming & Piercing | 14 | 7 | 14 | 12 | 20 | 16 | 5 | 2 | 90 days | |
Cooling Equipment | 35 days | |||||||||
Checking Fixture | 35 days |